Customer | Description |
Gunung Bayan Pratamacoal, PT (G. Bayan, East Kalimantan) |
Turnkey Project for : Coal handling plant facilities, consists of : Coal Crushing Plant 500 TPH Stacking Conveyor System 500 TPH Barge Loading Conveyor 1000 TPH |
Dermaga Perkasa Pratama, PT (Tg. Batu, East Kalimantan) |
Turnkey Project for : Incoming Coal Facility for Balikpapan Coal Terminal, Phase 3A: Incoming Line of 2400 TPH Stacking Conveyor System 2400 TPH |
Kalimantan Citra Bara, PT (Senoni, East Kalimantan) |
Turnkey Project for : Coal handling plant facilities, consists of : Coal Crushing Plant 500 TPH Stacking Conveyor system 500 TPH Barge Loading Conveyor 1000 TPH |
Riau Andalan Pulp and paper, PT (P. Kerinci, Riau) |
Turnkey Project for : Fuel handling system for power boiler 3 Reclaiming Conveyor System 500 TPH Boiler Feeding Conveyors 1000 TPH |
Asia Energy Indonesia, PT (Sanga-sanga, East Kalimantan) |
Build, Operate and Own (BOO) for : Coal Crushing 350 TPH Barge Loading Conveyor 750 TPH And Jetty System |
Multi Prima Energi, PT (Loa Raya, East Kaliamantan) |
Build, Operate and Own (BOO) for : Coal Crushing 250 TPH Barge Loading Conveyor 500 TPH And Jetty System |
Gema Rahmi Persada, PT (Rimba Ayu, Kota Bangun, East Kalimantan) |
1. Turnkey Project for : Coal handling plant facilities, consists of : Coal Crushing Plant 350 TPH Stacking Conveyor sytem 500 TPH Barge Loading Conveyor 1000 TPH 2. Operating and Maintenance for : - Coal Handling Pland and Facility |
Yasa Industri Nusantara, PT (Perawang, IKPP, Riau) |
Turnkey Project for : Fabrication and installation for Piping System at IKPP Facility |
Marunda Grahamineral, PT (Bengkoang, Central Kalimantan) |
Turnkey Project for : Intermediate coal stockpile phase II - Incoming Capacity 1000 TPH - Stockpiling Capacity 1000 TPH - Outgoing Capacity 1000 TPH |
Titan Mining Indonesia, PT (Muara Kilis, Jambi) |
Turnkey Project for : Installation Coal Dryer system and Facility |
Bumi Borneo Inti, PT (Talang Dukuh, Jambi) |
Build, Operate and Own (BOO) for : Coal Stockpiling and Management, Barge Loading Conveyor 1000 TPH And Jetty System |
Zen Jaya Indonesia, PT (Berau, East Kalimantan) |
Build, Operate and Own (BOO) for : Coal Crushing 500 TPH Barge Loading Conveyor 1000 TPH And Jetty System |
Asmin Koalindo Tuhup, PT (Muara Tuhup, Central Kalimantan |
Turnkey Project for : Barge loading Conveyor Cap. 2.400 TPH & Reclaim Feeder Fuel Tank & Piping system Cap. 3000 KL Coal Crushing Plant 850 TPH |
Artha Contractors, PT (Damparan, Central Kalimantan) |
Turnkey Project for : Intermediate Stockpile (ISP) system. Incoming Capacity Max. 3000 TPH Outgoing Capacity Max. 4000 TPH |
Kalimantan Energi Lestari, PT (Batu Licin, South Kalimantan) |
Built Project for : Coal Handling Plant Facilities Capacity 600 TPH |
Asmin Koalindo Tuhup, PT (Muara Tuhup, Central Kalimantan) |
Built Project for : Coal Screening Cap.250 TPH |
Marunda Grahamineral, PT (Bengkoang, Central Kalimantan) |
Built Project for : Mooring Dolphine 2 Unit |
Asmin Bara Bronang, PT (Kapuas, Central Kalimantan) |
Built Project for : Feeding Facility Washing Plan |
IMR Anugrah Greens, PT (Murung Raya, Central Kalimantan) |
Built Project for : Barge Loader Cap. 2000 TPH |
Bina Sukses Insan Mandiri (Marimun, East Kalimantan) |
Built Project for : Crushing Plant Facility 1.000 TPH Barge Loader Conveyor 1.500 TPH |